1. Consideration of the second reading to occur September 28, 2015
2. Public hearing announcement – Monday, October 12, 2015, beginning at 6:00 p.m. in Council Chambers, Administration Building, Beaufort County Government Robert Smalls Complex, 100 Ribaut Road, Beaufort
3. First reading approval occurred September 14, 2015 / Vote 9:0
4. Governmental Committee discussion occurred September 14, 2015
1. Funding source: $250,000 from SCDOT and $294,873 from the Bluffton Parkway 5A Segment 2 Sales Tax Account #47010012-54500 with an available balance of $2,758,738
2. Public Facilities Committee discussion and recommendation to accept SCDOT cost sharing proposal of $250,000 for the full depth patching and resurfacing of the remaining portion of U.S. Highway 278 to Bowers Bridge occurred September 21, 2015 / Vote 6:0
1. Consideration of the second reading to occur September 28, 2015
2. Public hearing announcement – Monday, October 12, 2015, beginning at 6:00 p.m. in Council Chambers, Administration Building, Beaufort County Government Robert Smalls Complex, 100 Ribaut Road, Beaufort
3. First reading approval occurred September 14, 2015 / Vote 9:0
4. Governmental Committee discussion occurred September 14, 2015
1. Funding source: $250,000 from SCDOT and $294,873 from the Bluffton Parkway 5A Segment 2 Sales Tax Account #47010012-54500 with an available balance of $2,758,738
2. Public Facilities Committee discussion and recommendation to accept SCDOT cost sharing proposal of $250,000 for the full depth patching and resurfacing of the remaining portion of U.S. Highway 278 to Bowers Bridge occurred September 21, 2015 / Vote 6:0